Title
Construct Storm Water Repair and Improvements
Action
Action:
A. Approve a contract in the amount of $3,697,073 to the lowest responsive bidder OnSite Development, LLC for the Storm Water Repair and Improvement FY2022-A project,
B. Approve a contract in the amount of $3,697,073 to the lowest responsive bidder OnSite Development, LLC for the Storm Water Repair and Improvement FY 2022-B project,
C. Approve a contract in the amount of $3,903,251 to the lowest responsive bidder OnSite Development, LLC for the Storm Water Repair and Improvement FY 2022-C project, and
D. Approve a contract in the amount of $3,856,448.09 to the lowest responsive bidder United of Carolinas, Inc. for the Storm Water Repair and Improvement FY 2022-D project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Susan Tolan, Storm Water Services
Explanation
* These contracts are part of an ongoing program to provide repairs and/or improvements to storm drainage systems.
* Approximately 25 projects may be constructed from each contract, within a contract term that may not exceed 24 months. The number of projects may vary depending on the nature and extent of the repairs constructed.
Action A
* On August 4, 2021, the City issued an Invitation to Bid; three bids were received.
* OnSite Development, LLC was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by the second quarter of 2023.
Action B
* On August 4, 2021, the City issued an Invitation to Bid; three bids were received.
* OnSite Development, LLC was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by the second quarter of 2023.
Action C
* On August 9, 2021, the City issued an Invitation to Bid; three bids were received.
* OnSite Development, LLC was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by the second quarter of 2023....