Title: Collective Storm Drainage Improvement Project Series E
Attachments: 1. Map_Collective Storm Drainage Improvement Project Series E.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.
Title
Collective Storm Drainage Improvement Project Series E

Action
Action:
Approve a contract in the amount of $1,784,200 to the lowest responsive bidder Zoladz Construction Co., Inc. for the Collective Storm Drainage Improvement Project Series E.

Staff Resource(s):
Phil Reiger, General Services
Mike Davis, General Services
Susan Tolan, General Services

Explanation
* This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems.
* This contract will address failing storm drainage systems in the following locations:
* 15611 Sullivans Ridge Drive located in Council District 7,
* 3529 Selwyn Farms Lane located in Council District 1,
* 6600 CSX Way located in Council District 3,
* 2332 Harwood Hills Lane located in Council District 2,
* 9139 Eventine Court located in Council District 2,
* 7204 War Emblem Court located in Council District 2,
* 9325 Lake Spring Avenue located in Council District 2,
* 2304 Hope Valley Lane located in Council District 4,
* 6401 Covecreek Drive located in Council District 1, and
* 7704 Grapetree Court located in Council District 5.
* Work will also include grading, drainage, sidewalks, and curb and gutter.
* On May 4, 2020, the city issued an Invitation to Bid; five bids were received.
* Zoladz Construction Co., Inc. was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by fourth quarter 2021.

Charlotte Business INClusion
Established MBE Goal: 7.00%
Committed MBE Goal: 9.31%
Zoladz Construction Co., Inc. met the established MBE subcontracting goal and has committed 9.31% ($166,156) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Diamond Trucking of NC Inc (MBE, SBE) ($103,156) (hauling)
* R.R.C. Concrete Inc. (MBE, SBE) ($63,000) (concrete)

Established SBE Goal: 18.00%
Committed SBE Goal: 18.00%
Zoladz Construction Co., Inc. met the established SBE ...