File #: 15-13598    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 6/15/2020 In control: City Council Business Meeting
On agenda: 7/13/2020 Final action:
Title: Collective Storm Drainage Improvement Project Series E
Attachments: 1. Map_Collective Storm Drainage Improvement Project Series E.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Collective Storm Drainage Improvement Project Series E

 

Action

Action:

Approve a contract in the amount of $1,784,200 to the lowest responsive bidder Zoladz Construction Co., Inc. for the Collective Storm Drainage Improvement Project Series E.

 

Staff Resource(s):

Phil Reiger, General Services

Mike Davis, General Services

Susan Tolan, General Services

 

Explanation

§                     This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems.

§                     This contract will address failing storm drainage systems in the following locations:

-                     15611 Sullivans Ridge Drive located in Council District 7,

-                     3529 Selwyn Farms Lane located in Council District 1,

-                     6600 CSX Way located in Council District 3,

-                     2332 Harwood Hills Lane located in Council District 2,

-                     9139 Eventine Court located in Council District 2,

-                     7204 War Emblem Court located in Council District 2,

-                     9325 Lake Spring Avenue located in Council District 2,

-                     2304 Hope Valley Lane located in Council District 4,

-                     6401 Covecreek Drive located in Council District 1, and

-                     7704 Grapetree Court located in Council District 5.

§                     Work will also include grading, drainage, sidewalks, and curb and gutter.

§                     On May 4, 2020, the city issued an Invitation to Bid; five bids were received.

§                     Zoladz Construction Co., Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2021.

 

Charlotte Business INClusion

Established MBE Goal: 7.00%

Committed MBE Goal: 9.31%

Zoladz Construction Co., Inc. met the established MBE subcontracting goal and has committed 9.31% ($166,156) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Diamond Trucking of NC Inc (MBE, SBE) ($103,156) (hauling)

§                     R.R.C. Concrete Inc. (MBE, SBE) ($63,000) (concrete)

 

Established SBE Goal: 18.00%

Committed SBE Goal: 18.00%

Zoladz Construction Co., Inc. met the established SBE subcontracting goal and has committed 18.00% ($321,156) of the total contract amount to the following SBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     On Time Construction, Inc. (WBE, SBE) ($155,000) (masonry)

§                     Diamond Trucking of NC Inc (MBE, SBE) ($103,156) (hauling)

§                     R.R.C. Concrete Inc. (MBE, SBE) ($63,000) (concrete)

 

Fiscal Note

Funding:  Storm Water Capital Investment Plan

 

Attachments

Attachment(s)

Map