City of Charlotte Banner
File #: 15-7982    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 4/6/2018 In control: City Council Business Meeting
On agenda: 5/30/2018 Final action: 5/30/2018
Title: Storm Drainage Improvement Projects Series A
Attachments: 1. Location Map - Collective Storm Drainage Improvements Projects Series A
Title
Storm Drainage Improvement Projects Series A

Action
Action:
Award a contract in the amount of $1,398,164.58 to the lowest responsive bidder Sealand Contractors Corp. for the Storm Drainage Improvement Projects Series A.

Body
Staff Resource(s):
Mike Davis, Engineering and Property Management
Bong Vang, Engineering and Property Management

Explanation
* This contract is part of an ongoing program to provide repairs and improvements to existing storm drainage systems and construction of new storm drainage systems.
* Each request is investigated and prioritized based on the severity of potential public/private property flooding and/or property damage.
* The necessary repairs for each project are designed and a work order prepared.
* Contract A will address failing storm drainage systems in the following locations:
* 3211 Ernest Russell Court (Council District 4),
* 12516 Headquarters Farm Road (Council District 4),
* 530 Halliwell Street (Council District 4),
* 3711 Millstream Ridge Drive (Council District 4).
* 815 Wabash Avenue (Council District 2),
* 811 Trailing Rock Drive (Council District 2),
* 1222 Norris Avenue (Council District 1),
* 2869 Oasis Lane (Council District 3).
* Work will also include grading, drainage, sidewalks, curb and gutter, and water mains and services to existing infrastructure that increases safety and provides maintenance upgrades to roads.
* On April 13, 2018, the City issued an Invitation to Bid for Collective Storm Drainage Improvement Projects Series A; five bids were received from interested service providers.
* Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.
* These projects are anticipated to be complete by end of first quarter 2019.

Charlotte Business INClusion
Established SBE Goal: 17.00%
Committed SBE Goal: 17.00%
Sealand met the established subcontracting goal, and has committed 17% ($237,688) of the total contract amount to the following certified firms (Part B: Section 3...

Click here for full text