File #: 15-5730    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 5/30/2017 In control: City Council Business Meeting
On agenda: 1/22/2018 Final action: 1/22/2018
Title: Airport Vehicle Maintenance Facility Construction
Attachments: 1. Airport ORD012218 - Airport Vehicle Maintenance Facility Construction, 2. Walbridge RCA GFE Summary
Title
Airport Vehicle Maintenance Facility Construction

Action
Action:
A. Award a contract in the amount of $14,284,079 to the lowest responsive bidder Walbridge Southeast LLC for the Airport Vehicle Maintenance Facility, and

B. Adopt a budget ordinance appropriating $2,684,079 from the Aviation Discretionary Fund to the Aviation Community Investment Plan Fund.

Body
Staff Resource(s):
Brent Cagle, Aviation
Jack Christine, Aviation

Explanation
* This project is for the construction of the Airport Vehicle Maintenance Facility to be located at 3701 Harlee Avenue (Council District 5).
* The facility will consist of 19 maintenance bays to accommodate 561 pieces of rolling stock, including light and heavy vehicles. The facility will also have a parts storage area, vehicle wash bay, and office space.
* On April 17, 2017, the City issued an Invitation to Bid; eight bids were received.
* The original bid was protested because of equipment specifications and pricing. After further review, Aviation decided to issue a second solicitation considering these factors.
* On October 31, 2017, the City issued a new Invitation to Bid; four bids were received.
* Walbridge Southeast LLC was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by summer of 2019.
* Due to previous appropriations of 2017A Bonds, only $2,684,079 is needed for the budget ordinance to fully fund this contract.

Charlotte Business INClusion
Established SBE Goal: 10.00%
Committed SBE Goal: 8.41%

Walbridge Southeast, LLC failed to meet the SBE goal at bid opening, but exceeded the minimum Good Faith Efforts points (Part B: Section 5 of the Charlotte Business INClusion Policy). Walbridge Southeast, LLC's initial SBE commitments totaled 8.41% ($1,200,800) of the total contract amount to the following certified firms:
* Harco Development, Inc. (SBE) ($761,094) (site work package, erosion control, site demolition and clearing, grading, storm water drai...