Title
Construction Manager at Risk for Firehouse No. 46 Infill Station Project
Action
Action:
Approve a contract in the amount of $17,337,294 with J.E. Dunn - McFarland, A Joint Venture, for construction phase services of the Firehouse No. 46 Infill Station Construction Manager at Risk project.
Body
Staff Resource(s):
Phil Reiger, General Services
Kathleen Cishek, General Services
Mary Herington, General Services
Explanation
* Charlotte Firehouse No. 46 was identified in the Construct Fire Facilities Program and was approved in the Fiscal Year 2024 Adopted Budget.
* Charlotte Firehouse No. 46 will be a 14,600 square-foot in-fill firehouse at 4032 Miranda Road in Council District 2.
* The city has selected the Construction Manager at Risk (CMAR) project delivery method to provide more effective coordination, more certainty with project costs, and to fast track the schedule and better mitigate risks during construction.
* On April 2, 2024, the city issued a Request for Qualifications (RFQ); ten proposals were received.
* J. E. Dunn - McFarland, A Joint Venture, is the best qualified firm to meet the city's needs on the basis of demonstrated competence and qualification of professional services in response to the RFQ requirements.
* The contract with J. E. Dunn - McFarland is for construction phase services, including coordinating all construction activities, managing all subcontractors, and delivering the project in collaboration with the city and the design consultant.
* The pre-construction phase was awarded to J. E. Dunn - McFarland in March 2025, in the amount of $49,116.
* The project is anticipated to be complete by the second quarter of 2027.
Charlotte Business INClusion
The city has negotiated an overall project goal of 15.00% MBE and 10.00% WSBE. Because this is a Construction Manager at Risk, J. E. Dunn - McFarland has the opportunity to add Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE), or Small Business En...