Title: Airport Concourse A Expansion Phase 2 Design Amendment
Title
Airport Concourse A Expansion Phase 2 Design Amendment

Action
Action:
Approve contract amendment #6 for $528,713 to Perkins+Will North Carolina, Inc. for design services for the Concourse A Expansion Phase 2 project.

Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation

Explanation
* On March 25, 2019, City Council approved a contract with Perkins+Will North Carolina, Inc. in the amount of $8,428,000 to provide design services for the Concourse A Expansion Phase 2 (CAP2) Project. When the original contract was approved by Council, Aviation noted the intent to return to Council with additional actions to approve a construction contract and an amendment to this contract for construction administration based on the design phase.
* This amendment includes full design and construction administration services for a new baggage handling system Make-up Device (MU8) Expansion at the CAP2 mid-connector.
* Previous amendments to this contract include:
* Amendment #1 in the amount of $70,565 to include additional design and bidding phase commissioning,
* Amendment #2 in the amount of $449,802.47 to include baggage handling system revisions and modifications to the Delta Airlines Club tenant space.
* Amendment #3 in the amount of $20,000 to include design for modifications to the chilled and heating hot water distribution,
* Amendment #4 in the amount of $18,000 to include the design of a single-user restroom at Concourse A1 mid-connector, and
* Amendment #5 in the amount of $4,008,000 to include construction administration services. When the original contract was approved by Council, Aviation noted the intent to return to Council with additional actions to approve a construction contract and an amendment to this contract for construction administration.
* New total contract expenditures including all amendments is $13,523,880.47.

Charlotte Business INClusion
All additional work involved in this Contract Amendment will be performed by Perki...