Title: Construct Delane 1220 Storm Drainage Improvement Project
Attachments: 1. DelanelocationMap

Title

Construct Delane 1220 Storm Drainage Improvement Project

 

Action

Action                     

Approve a contract in the amount of $1,252,025.70 to the lowest responsive bidder GreenWater Development Inc. for the Delane Avenue 1220 Storm Drainage Improvement Project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Matthew Gustis, Storm Water Services

 

Explanation

§                     This project will reduce street flooding and improve aging infrastructure in the McMullen Creek watershed along Delane Avenue and Castleton Road, in District 5.

§                     Construction will include the installation of storm drainage, water/sanitary sewer, curb, gutter, and driveways.

§                     On May 11, 2023, the city issued an Invitation to Bid; seven bids were received.

§                     GreenWater Development Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the third quarter of 2024.

 

Charlotte Business INClusion

Established MBE Goal: 10.00%

Committed MBE Goal: 10.03%

GreenWater Development, Inc. met the established subcontracting goal and has committed 10.03% ($125,566) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     RRC Concrete, Inc. (MBE) ($74,851) (concrete)

§                     Redstone Materials (MBE, SBE) ($50,715) (hauling)

 

Established SBE Goal: 20.00%

Committed SBE Goal: 20.05%

GreenWater Development, Inc. met the established subcontracting goal and has committed 20.05% ($250,987) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     RAM Pavement Services, Inc. Firm (SBE) ($105,044) (milling and paving)

§                     On Time Construction, Inc. (SBE, WBE) ($82,800) (masonry)

§                     S&G Express, LLC (SBE) ($63,143) (hauling)

 

Fiscal Note

Storm Water Capital Investment Plan

Attachments