City of Charlotte Banner
File #: 15-20423    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 5/17/2023 In control: City Council Business Meeting
On agenda: 6/26/2023 Final action: 6/26/2023
Title: Water Transmission Main Improvements and Repairs
Attachments: 1. RCA June 2023 - Map - Water Transmission Main Improvements and Repairs.pdf

Title

Water Transmission Main Improvements and Repairs

 

Action

Action:

Approve a guaranteed maximum price of $11,581,852.00 to State Utility Contractors, Inc. for Design-Build construction services for the Water Transmission Main Improvements and Repairs project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     State Utility Contractors, Inc. developed a guaranteed maximum price (GMP) for construction of a 30-inch water transmission main between Interstate 77, through the Elmwood Cemetery, along Cedar Street to 5th Street (Council District 2).

§                     The GMP also includes an improved water main along Cates Avenue to connect to the proposed transmission main (Council District 2).

§                     On June 8, 2020, City Council approved a contract with State Utility Contractors, Inc. for Design-Build services.

§                     This project is anticipated to be complete by fourth quarter 2024.

 

Charlotte Business INClusion

The city negotiates participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.7 of the Charlotte Business INClusion Policy). State Utility Contractors, Inc. has committed $1,240,378 or approximately 10.71% of the total contract for Design-Build construction services to the following certified firms:

                     Trull Contracting, LLC (SBE, WBE) ($482,000) (asphalt repair)

                     Fuller & Co. Construction, LLC (SBE) ($395,713) (trenchless crossing)

                     Buffkin Trucking, Inc. (MBE, SBE) ($208,000) (hauling)

                     Pentacle, In. (SBE, WBE) ($54,600) (fence repair)

                     Froehling & Robertson, Inc. (MBE) (50,300) (soil testing)

                     Stewart Engineering, Inc. (MBE) ($49,765) (surveying)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments

Attachment

Map