Title
Airport Terminal Lobby Expansion Construction Change Order
Action
Action:
Approve change order #1 for $1,381,211 to Holder Edison Foard Leeper - A Joint Venture for the Terminal Lobby Expansion project.
Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation
Explanation
§ The Terminal Lobby Expansion (TLE) project is currently underway at the Airport. Floor plans for the TLE were re-evaluated during the construction phase, to accommodate anticipated growth of the terminal operation.
§ This change order will provide for space reallocations on the basement, baggage, and ticket levels to meet the needs of Business & Innovation, Airport Operations, and Airline Operations.
§ On October 28, 2019, City Council approved a Construction Manager at Risk services contract with Holder Edison Foard Leeper - A Joint Venture, with a guaranteed maximum price of $500,277,842.21.
§ The new total of the contract, including this amendment, will be $501,659,053.21.
Charlotte Business INClusion
All additional work involved in this Change Order will be performed by Holder Edison Foard Leeper - A Joint Venture and their existing subcontractors (Part D: Section 6 of the Charlotte Business INClusion Policy).
Fiscal Note
Funding: Aviation Capital Investment Plan