File #: 15-18451    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 7/27/2022 In control: City Council Business Meeting
On agenda: 9/12/2022 Final action: 9/12/2022
Title: Stowe Regional Water Resource Recovery Facility Construction Phase 2
Attachments: 1. Map-Stowe Regional Water Resource Recovery Facility Construction Phase 2

Title

Stowe Regional Water Resource Recovery Facility Construction Phase 2

 

Action

Action:

Approve a guaranteed maximum price of $11,511,620 to Crowder/Garney JV for Design-Build construction services for the Stowe Regional Water Resource Recovery Facility project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Ron Hargrove, Charlotte Water

 

Explanation

§                     Crowder/Garney JV has developed a guaranteed maximum price (GMP) for preliminary sitework, primary clarifiers, and instrumentation and controls that will be used during the construction of the Stowe Regional Water Resource Recovery Facility (SRWRRF) project (adjacent to Council Districts 2 and 3).

§                     The SRWRRF will treat flows from the existing Long Creek basin and flows from the cities of Mount Holly and Belmont. 

§                     On April 27, 2020, and January 25, 2021, City Council approved contracts totaling $31,416,107 with Crowder/Garney JV for Design-Build design services.

§                     On February 14, 2022, and May 31, 2022, City Council approved GMPs totaling $50,757,414 with Crowder/Garney JV for the procurement of equipment and preliminary site work.

§                     City Council will receive future requests for the approval of additional construction. The SRWRRF is estimated to be in operation by second quarter 2026.

 

Charlotte Business INClusion

The city negotiates participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.4 of the Charlotte Business INClusion Policy). Crowder/Garney JV has committed $635,437 or approximately 5.52% with the following certified firms:

§                     Kingdom Trucking LLC (MBE, SBE) ($261,220) (purchasing and trucking of aggregates)

§                     Collins Reinforcing, Inc. (WBE) ($162,750) (rebar installation)

§                     HG Global Services, Inc. (SBE) ($86,165) (primary clarifiers metals)

§                     Lil Associates II, Inc. (MBE, SBE) ($75,000) (charlotte business inclusion participation consultant)

§                     Pedulla Trucking Excavating & Paving, Inc. (WBE) ($34,302) (primary clarifiers excavation)

§                     The Survey Company, Inc. (SBE) ($16,000) (land surveyor and global positioning system services)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan