Title: Charlotte-Mecklenburg Government Center HVAC Replacement Construction Manager at Risk Contract
Title
Charlotte-Mecklenburg Government Center HVAC Replacement Construction Manager at Risk Contract

Action
Action:
Authorize the City Manager to negotiate and approve a contract with J.E. Dunn Construction Company for a construction manager at risk in an amount not to exceed $960,000 for the construction phase of the Charlotte-Mecklenburg Government Center HVAC Replacement Project.

Body
Staff Resource(s):
Phil Reiger, General Services
Jennifer Smith, General Services
Kathleen Cishek, General Services

Explanation
* The Charlotte-Mecklenburg Government Center was completed in 1986. The majority of the heating, ventilation, and air conditioning (HVAC) equipment is original to the building. The HVAC equipment is beyond its useful life and in need of replacement to ensure proper heating, cooling, and air flow throughout the building.
* In December 2021, one of the two boilers failed and was unable to be repaired. This contract will allow the project to expedite the boiler replacement portion of the project.
* The City has selected the Construction Manager at Risk (CMAR) project delivery method to provide more effective coordination and more certainty with project costs and to fast track the schedule and better mitigate risks during construction.
* On October 27, 2020, the City issued a Request for Qualifications (RFQ); two proposals were received.
* J.E. Dunn Construction Company is the firm best qualified to meet the City's needs on the basis of demonstrated competence and qualification of professional services in response to the RFQ requirements.
* The contract with J.E. Dunn Construction Company is for construction phase services, including coordinating all construction activities, managing all subcontractors, and delivering the project in collaboration with the City and the design consultant.
* The pre-construction phase was awarded to J.E. Dunn Construction Company on June 14, 2021, in the amount of $383,778.
* City Council will be asked to ap...