City of Charlotte Banner
File #: 15-16890    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 11/15/2021 In control: City Council Business Meeting
On agenda: 1/10/2022 Final action: 1/10/2022
Title: Construct Storm Water Repair and Improvements
Title
Construct Storm Water Repair and Improvements

Action
Action:
A. Approve a contract in the amount of $3,913,468.26 to the lowest responsive bidder United of Carolinas, Inc. for the Storm Water Repair and Improvement FY2022-E project,

B. Approve a contract in the amount of $3,961,924.00 to the lowest responsive bidder OnSite Development, LLC. for the Storm Water Repair and Improvement FY 2022-F project,

C. Approve a contract in the amount of $4,271,453.75 to the lowest responsive bidder OnSite Development, LLC. for the Storm Water Repair and Improvement FY 2022-G project, and

D. Approve a contract in the amount of $4,253,394.80 to the lowest responsive bidder United of Carolinas Inc. for the Storm Water Repair and Improvement FY 2022-H project.

Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Susan Tolan, Storm Water Services

Explanation
? These contracts are part of an ongoing program to provide repairs and/or improvements to storm drainage systems.
? Approximately 25 projects may be constructed from each contract, within a contract term that may not exceed 24 months. The number of projects may vary depending on the nature and extent of the repairs constructed.

Action A
? On October 15, 2021, the City issued an Invitation to Bid; four bids were received.
? United of Carolinas, Inc. was selected as the lowest responsive, responsible bidder.
? The project is anticipated to be completed by the first quarter of 2024.

Action B
? On October 15, 2021, the City issued an Invitation to Bid; four bids were received.
? OnSite Development, LLC. was selected as the lowest responsive, responsible bidder.
? The project is anticipated to be completed by the first quarter of 2024.

Action C
? On October 21, 2021, the City issued an Invitation to Bid; four bids were received.
? OnSite Development, LLC was selected as the lowest responsive, responsible bidder.
? The project is anticipated to be completed by the firs...

Click here for full text