Title
Construct Lakeview Road Improvements Project
Action
Action:
Approve a contract in the amount of $8,505,897.30 to the lowest responsive bidder Blythe Development Co. for the Lakeview Road Improvements project.
Body
Staff Resource(s):
Phil Reiger, General Services
Jennifer Smith, General Services
Veronica Wallace, General Services
Explanation
§ This project will add transportation capacity along Lakeview Road from Cushing Drive to Old Statesville Road (approximately 1.5 miles) in Council District 2.
§ Improvements will include pavement upgrades, intersection modifications, additional through/turning lanes, drainage infrastructure, and pedestrian and bicycle facilities.
§ This project is 100 percent funded by the Federal Surface Transportation Block Grant Program and Direct Attributable and State Bonus Allocation.
§ On August 18, 2021, the City issued an Invitation to Bid; three bids were received.
§ Blythe Development Co. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by the end of fourth quarter 2024.
Disadvantage Business Enterprise
Established DBE Goal: 14.00%
Committed DBE Goal: 14.46%
Blythe Development Co. exceeded the established subcontracting goal and has committed 14.46% ($1,229,908) of the total contract amount to the following certified firm:
§ RRC Concrete Inc. (DBE) ($1,229,908) (concrete)
Fiscal Note
General Capital Investment Plan
Attachments
Attachment(s)
Map