Title: Construct Lakeview Road/Reames Road Intersection Project
Attachments: 1. Map_Construct Lakeview Road-Reames Road Intersection Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Construct Lakeview Road/Reames Road Intersection Project

 

Action

Action                     

Approve a contract in the amount of $5,117,804 to the lowest responsive bidder Sealand Contractors Corp. for the Lakeview Road/Reames Road Intersection project.

 

Body

Staff Resource(s):

Phil Reiger, General Services
Jennifer Smith, General Services

Veronica Wallace, General Services

 

Explanation

§                     This project will include the construction of a roundabout at the intersection of Lakeview Road and Reames Road and a sidewalk (approximately 1.5 miles) on Lakeview Road from Beatties Ford Road to Crushing Drive east of Reames Road in Council District 2.

§                     Work will include sidewalk, planting strips, curb and gutter, storm drainage, water main, grading, tree clearing, asphalt pavement, accessible ramps, and pavement markings.

§                     This project will improve traffic flow at the intersection for the future direct connection to the North Carolina Department of Transportation (NCDOT) Interstate 77 High Occupancy Toll Lanes project.

§                     The project will also connect to the Lakeview Road Farm-To-Market project from Cushing Drive to Old Statesville Road.

§                     NCDOT contributed $2 million to the project in 2018 ($1 million Congestion Mitigation and Air Quality Improvement Program and $1 million Charlotte Regional Transportation Planning Organization bonus allocation funding).

§                     On July 21, 2021, the City issued an Invitation to Bid; four bids were received.

§                     Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.

§                     Construction is anticipated to be completed by second quarter 2024.

 

Disadvantaged Business Enterprise

Established DBE Goal:  14.00%

Committed DBE Goal:  14.00%

Sealand Contractors Corp. has committed 14.00% ($716,551) of the total contract amount to the following certified firms:

§                     Darnell Jones Trucking (DBE) ($292,725) (hauling)

§                     Diamond Trucking of NC Inc. (DBE) ($274,425) (hauling)

§                     On Time Construction Inc. (DBE) ($65,745) (drainage structures, endwalls and block wall installation)

§                     BC Cannon Co Inc. (DBE) ($15,605) (permanent signs)

§                     McCain Striping Service Inc. (DBE) ($68,051) (pavement markings)

 

Fiscal Note

Funding:  General Capital Investment Plan

 