File #: 15-16270    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 8/4/2021 In control: City Council Business Meeting
On agenda: 10/11/2021 Final action: 10/11/2021
Title: Mount Holly Pump Station and Force Main Construction
Attachments: 1. Map-Mount Holly Pump Station and Force Main Construction
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Mount Holly Pump Station and Force Main Construction

 

Action

Action:

Approve a guaranteed maximum price of $41,010,129 to The Haskell Company for Design-Build construction services for the Mount Holly Pump Station and Force Main project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     The Haskell Company has developed a guaranteed maximum price (GMP) for the construction of several pipelines which will enable the City of Mount Holly to convey sanitary sewer flow to the future Stowe Regional Water Resource Recovery Facility (adjacent to Council Districts 2 and 3).

§                     On July 8, 2019, City Council approved a contract for $8,848,918 with The Haskell Company for Design-Build design services.

§                     On March 16 and September 14, 2020, City Council approved GMPs of $829,219 and $1,122,311 with The Haskell Company for the procurement of specialized materials, equipment, and associated preconstruction services for the existing facilities.

§                     On May 10, 2021, City Council approved a contract amendment for $3,000,000 for additional value engineering design services.

§                     City Council will receive future requests for the approval of remaining project GMPs once they are established.

 

Charlotte Business INClusion

This project is subject to the North Carolina Clean Water State Revolving Fund project guidelines, which only require MWBE goals on construction contracts. The Haskell Company has committed $2,668,690 or approximately 6.51% of the Design-Build construction services to the following certified firms:

§                     Pedulla Trucking Excavating & Paving, Inc. (WBE) ($2,236,110) (earthwork)

§                     Pentacle, Inc. (WBE, SBE) ($164,850) (fencing and gates)

§                     Diva Dumps, LLC (MBE) ($107,050) (temporary toilets, dumpsters, HDD solids trucking)

§                     Piedmont Electrical Distributors of Greenville (SBE) ($92,380) (electrical distributor)

§                     Flawless Capture Photography (SBE) ($30,000) (preconstruction and progress photo and video)

§                     TKG, PLLC (WBE, SBE) ($30,000) (eBuilder document control)

§                     The Survey Company (SBE) ($7,500) (survey and easement mapping)

§                     Avioimage Mapping Services, Inc. (SBE) ($800) (aerial survey)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments

Attachment(s)

Map