Title: Stowe Regional Water Resource Recovery Facility Southern Access Bridge
Attachments: 1. Map-Stowe Regional Water Resource Recovery Facility Southern Access Bridge

Title

Stowe Regional Water Resource Recovery Facility Southern Access Bridge

 

Action

Action                     

Approve a contract in the amount of $3,853,951.20 to the lowest responsive bidder Blythe Development Company for the Stowe Regional Water Resource Recovery Facility Southern Access Bridge project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This contract is for the construction of a bridge over Long Creek as part of the access road to the Stowe Regional Water Resource Recovery Facility (RWRRF) (adjacent to Council Districts 2 and 3).

§                     Charlotte Water is currently in the design phase of the Stowe RWRRF. This project will construct the first of two driveways to the property to ensure adequate access.

§                     On June 14, 2021, the City issued an Invitation to Bid (ITB); two bids were received.

-                     G.S. 143-132 prohibits municipalities from awarding construction contracts over $500,000 without receiving at least three competitive bids from the initial advertisement of the contract. The City may subsequently award the contract even if re-advertisements result in fewer than three competitive bids.

§                     On July 13, 2021, the ITB was re-issued; two bids were received.

§                     Blythe Development Company was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2022.

 

Charlotte Business INClusion

Established MBE Goal: 3.00%

Committed MBE Goal: 1.78%

Blythe Development Company failed to meet the established MBE subcontracting goal but earned the minimum Good Faith Effort Points (Part B: Section 5 of the Charlotte Business INClusion Policy). Blythe Development Company has committed 1.78% ($68,512) of the total contract amount to the following certified firms:

§                     Express Logistics Services, Inc. (MBE, SBE) ($47,332) (hauling)

§                     Lopez Rebar, LLC (MBE) ($21,180) (tie rebar)

 

Established SBE Goal: 7.00%

Committed SBE Goal: 2.47%

Blythe Development Company failed to meet the established SBE subcontracting goal but earned the minimum Good Faith Effort Points (Part B: Section 5 of the Charlotte Business INClusion Policy). Blythe Development Company has committed 2.47% ($95,332) of the total contract amount to the following certified firms:

                     §                     Theresa Concrete (SBE) ($48,000) (concrete)

                     §                     Footprints Trucking (MBE, SBE) ($47,332) (hauling)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 