File #: 15-16237    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 8/2/2021 In control: City Council Business Meeting
On agenda: 9/27/2021 Final action: 9/27/2021
Title: Charlotte Water Operations Facility Construction
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Charlotte Water Operations Facility Construction

 

Action

Action                     

Approve a guaranteed maximum price of $40,771,800 to Rodgers Builders, Inc. for Construction Manager at Risk services for the Field Operations Zone 4 Facility Replacement project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This contract is for the Field Operations Zone 4 Facility Replacement project (Council District 3) which will provide reliable facilities to support employees across multiple divisions of Charlotte Water, including Field Operations, Workforce Development, Maintenance, and Storm Water Services.

§                     The project includes a new administration building, warehouse, vehicle wash, fueling station, and covered material storage area.

§                     On June 25, 2018, City Council approved a contract for $175,616 with Rodgers Builders, Inc. for pre-construction phase services for this project.

§                     The project is anticipated to be complete by second quarter 2023.

 

Charlotte Business INClusion

The City has established project goals of 9.00% MBE and 18.00% SBE. Because this is a Construction Manager at Risk project, the construction manager has the opportunity to add on MBE and SBE firms throughout the life of the project (Part G: Section 2.3 of the Charlotte Business INClusion Policy).

Fiscal Note

Funding: Charlotte Water Capital Investment Plan