Title
Charlotte Water Operations Facility Construction
Action
Action:
Approve a guaranteed maximum price of $40,771,800 to Rodgers Builders, Inc. for Construction Manager at Risk services for the Field Operations Zone 4 Facility Replacement project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ This contract is for the Field Operations Zone 4 Facility Replacement project (Council District 3) which will provide reliable facilities to support employees across multiple divisions of Charlotte Water, including Field Operations, Workforce Development, Maintenance, and Storm Water Services.
§ The project includes a new administration building, warehouse, vehicle wash, fueling station, and covered material storage area.
§ On June 25, 2018, City Council approved a contract for $175,616 with Rodgers Builders, Inc. for pre-construction phase services for this project.
§ The project is anticipated to be complete by second quarter 2023.
Charlotte Business INClusion
The City has established project goals of 9.00% MBE and 18.00% SBE. Because this is a Construction Manager at Risk project, the construction manager has the opportunity to add on MBE and SBE firms throughout the life of the project (Part G: Section 2.3 of the Charlotte Business INClusion Policy).
Fiscal Note
Funding: Charlotte Water Capital Investment Plan