File created: 5/24/2021 In control: City Council Business Meeting
On agenda: 8/9/2021 Final action: 8/9/2021
Title: Sugar Creek Sanitary Sewer Rehabilitation
Attachments: 1. Map-Sugar Creek Sanitary Sewer Rehabilitation

Title

Sugar Creek Sanitary Sewer Rehabilitation

 

Action

Action                     

A.                     Reject the low-bid submitted by Michels Pipe Services, Inc. for the Sugar Creek 78-inch Sanitary Sewer Rehabilitation project, and

 

B.                     Approve a contract in the amount of $6,485,671.84 to the lowest responsive bidder SAK Construction, LLC for the Sugar Creek 78-inch Sanitary Sewer Rehabilitation project.

 

Body

Staff Resource(s)

Angela Charles, Charlotte Water

Jackie Jarrell, Charlotte Water

Scott Clark, Charlotte Water

 

Explanation

§                     This project will rehabilitate 2,700 linear feet of 78-inch pipe by installing a liner within the existing Lower Sugar Creek Outfall near Carolina Place Mall in the Town of Pineville (adjacent to Council District 7).

§                     The new pipe lining is a corrosion-resistant product that is expected to extend the life of the sanitary sewer line an additional 50 years.

§                     On May 7, 2021, the city issued an Invitation to Bid; four bids were received.

§                     SAK Construction, LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by second quarter 2022.

§                     The low bid of $3,539,433.30 submitted by Michels Pipe Services, Inc. was found not to be responsible for failing to meet the CBI Good Faith Efforts requirements.

 

Charlotte Business INClusion

Established MBE Goal: 2.00%

Committed MBE Goal: 0.00%

SAK Construction, LLC failed to meet the established MBE subcontracting goal but earned the minimum Good Faith Effort Points (Part B: Section 5 of the Charlotte Business INClusion Policy).

 

Established SBE Goal: 2.00%

Committed SBE Goal: 2.26%

SAK Construction, LLC exceeded the established SBE subcontracting goal and has committed 2.26% ($146,750) of the total contract amount to the following certified firm (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Hampton Environmental & Construction, LLC (SBE) ($146,750) (excavations, manhole modifications)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments