Title: Construct Storm Drainage Improvements
Attachments: 1. Map_Construct Collective Storm Drainage Improvement Projects Series H

Title

Construct Storm Drainage Improvements

 

Action

Action                     

Approve a contract in the amount of $1,297,666.56 to the lowest responsive bidder Blythe Development Co. for Storm Drainage Improvement Projects Series H.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Susan Tolan, Storm Water Services

 

Explanation

§                     This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems.

§                     This contract will address failing storm drainage systems in the following locations:

-                     2606 Houston Branch Road (District 7), and

-                     2627 Moss Spring Road (District 7).

§                     Work includes replacement of storm drainage systems, curb and gutter, pipe lining, culvert repairs, and stream bank stabilization.

§                     On June 3, 2021, the city issued an Invitation to Bid; three bids were received.

§                     Blythe Development Co. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter of 2022.

 

Charlotte Business INClusion

Established MBE Goal: 7.00%

Committed MBE Goal: 7.01%

Blythe Development Co. exceeded the established MBE subcontracting goal and has committed 7.01% ($91,000) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Diamond Trucking of NC, Inc. (MBE, SBE) ($50,970) (hauling)

§                     RRC Concrete (MBE, SBE) ($40,030) (concrete)

 

Established SBE Goal: 15.00%

Committed SBE Goal: 15.00%

Blythe Development Co. met the established SBE subcontracting goal and has committeed 15.00% ($194,650) of the total contract amount to the following SBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     RRC Concrete, Inc. (MBE, SBE) ($140,900) (concrete, masonry)

§                     Ontime Construction, Inc. (WBE, SBE) ($44,000) (drainage structure)

§                     Pentacle, Inc.  (WBE, SBE) ($9,750) (fencing)

 