File #: 15-15477    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 3/23/2021 In control: City Council Business Meeting
On agenda: 4/26/2021 Final action:
Title: Construct Westinghouse Boulevard Multi-Use Path
Attachments: 1. Map_Construct Westinghouse Boulevard Multi-Use Path
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.
Title
Construct Westinghouse Boulevard Multi-Use Path

Action
Action:
Approve a contract in the amount of $3,975,597.45 to the lowest responsive bidder Eagle Wood, Inc. for the Westinghouse Boulevard Multi-Use Path project.

Body
Staff Resource(s):
Phil Reiger, General Services
Jennifer Smith, General Services
Veronica Wallace, General Services

Explanation
* Identified in the Whitehall Ayrsley Comprehensive Neighborhood Improvement Program, this project includes the construction of a multi-use path to improve pedestrian connectivity along Westinghouse Boulevard from South Tryon Street to Steele Creek Road in Council District 3.
* On February 19, 2021, the city issued an Invitation to Bid; six bids were received.
* Eagle Wood, Inc. was selected as the lowest responsive, responsible bidder.
* This project is anticipated to be complete by third quarter 2023.

Charlotte Business INClusion
Established MBE Goal: 7.00%
Committed MBE Goal: 7.04%
Eagle Wood, Inc. exceeded the established MBE subcontracting goal and has committed $280,000 or approximately 7.04% of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Martin Landscaping Company, Inc. (MBE, SBE) ($40,000) (seeding / mulching)
* Luvall Asphalt Services, Inc. (MBE, SBE) ($100,000) (asphalt paving/ milling)
* Streeter Trucking Company (MBE) ($60,000) (hauling)
* Mid Atlantic Erosion Control, INC. (MBE, SBE) ($80,000) (erosion control measure/ fencing)

Established SBE Goal: 19.00%
Committed SBE Goal: 19.12%
Eagle Wood, Inc. exceeded the established MBE subcontracting goal and has committed $760,000 or approximately 19.12% of the total contract amount to the following SBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):
* B&M Concrete, Inc. (MBE, SBE) ($760,000) (concrete curbs, gutter sidewalks, and multi-use paths)

Fiscal Note
Funding: General Capital Investment Plan