Title: Charlotte-Mecklenburg Government Center Generators Replacement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Charlotte-Mecklenburg Government Center Generators Replacement

 

Action

Action                     

Approve a contract in the amount of $906,000 to the lowest responsive bidder Miles-McClellan Construction Company, Inc. for the Charlotte-Mecklenburg Government Center Generators Replacement project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

David Wolfe, General Services

 

Explanation

§                     This project includes the replacement of emergency generators and switchgear in the basement of the Charlotte-Mecklenburg Government Center (CMGC) located in Council District 1.

§                     The current emergency generators are at the end of their useful lives. This project will ensure ongoing reliable emergency power to the CMGC fire protection and electrical systems. 

§                     On September 29, 2020, the city issued an Invitation to Bid; no bids were received. On November 12, 2020, the city re-issued an Invitation to Bid; two bids were received.

§                     Miles-McClellan Construction Company, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2021.

 

Charlotte Business INClusion

Established MBE Goal: 5.00%

Committed MBE Goal: 5.08%

 

Miles-McClellan Construction Company, Inc. met the established MBE subcontracting goal and has committed 5.08% ($46,000) of the total contract amount to the following certified MBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Carroll Small Repairs (MBE, SBE) ($45,000) (cleaning services)

§                     Richa Graphics (MBE, SBE) ($1,000) (plan printing)

 

Established SBE Goal: 11.00%

Committed SBE Goal: 45.29%

 

Miles-McClellan Construction Company, Inc. exceeded the established SBE subcontracting goal and has committed 45.29% ($410,372) of the total contract amount to the following certified SBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Armstrong Mechanical Services Inc. (SBE) ($409,277) (HVAC)

§                     Berry’s Container Service L.L.C. (SBE) ($600) (dumpster)

§                     Faith Cleaning Services, Inc (SBE) ($495) (cleaning)

Fiscal Note