Title
Airport CLT Center Renovations Phase 12 Construction
Action
Action:
Approve a contract in the amount of $1,583,891 to the lowest responsive bidder Edison Foard Construction Services, Inc. for the CLT Center Renovations Phase 12 project.
Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation
Explanation
§ This project consists of the conversion of approximately 7,000 square feet of warehouse space into the new Airport Operations Center (AOC) and Control Room within the CLT Center office complex.
§ This new space is necessary to relocate the AOC and Control Room due to the Terminal Lobby Expansion Project.
§ On September 8, 2020, the city issued an Invitation to Bid; 12 bids were received.
§ Edison Foard Construction Services, Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by third quarter 2021 (use calendar year).
§ This activity is occurring on airport property located in Council District 3.
Charlotte Business INClusion
Established MBE Goal: 5.00%
Committed MBE Goal: 21.18%
Edison Foard Construction Services exceeded the established subcontracting goal, and has committed 21.18% ($335,457) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ Superior Mechanical Systems (MBE) ($256,450) (mechanical)
§ NJR Construction, LLC (MBE) ($79,007) (drywall, metal framing, fire caulking)
Fiscal Note
Funding: Aviation Capital Investment Plan