Title: Stevens Creek Sanitary Sewer Phase 2
Attachments: 1. Map - Stevens Creek Sanitary Sewer Phase 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Stevens Creek Sanitary Sewer Phase 2

 

Action

Action                     

Approve a contract in the amount of $1,553,865.53 to the lowest responsive bidder Fuller & Co. Construction, LLC for the Stevens Creek Sanitary Sewer Phase 2 project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Ron Hargrove, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This project includes the replacement of approximately 4,000 linear feet of 12-inch gravity sanitary sewer and 600 linear feet of 8-inch gravity sewer serving the customers located in the Stevens Creek Basin in the Town of Mint Hill (adjacent to City Council District 5). This project includes the elimination of two small sanitary sewer lift stations.

§                     On August 7, 2020, the city issued an Invitation to Bid; six bids were received.

§                     Fuller & Co. Construction, LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2021.

 

Charlotte Business INClusion

Fuller & Co. Construction, LLC is a city certified SBE.

Established MBE Goal: 3.00%

Committed MBE Goal: 4.71%

 

Fuller & Co. Construction, LLC met the established subcontracting goal and has committed $73,158 or approximately 4.71% of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Buffkin Trucking, Inc. (MBE, SBE) ($73,158) (hauling)

 

Established SBE Goal: 0.00%

Committed SBE Goal: 5.96%

Fuller & Co. Construction, LLC also committed $92,625 or approximately 5.96% of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Maybury Fencing, Inc. (WBE, SBE) ($72,000) (fencing)

§                     The Survey Company, Inc. (SBE) ($15,000) (construction staking and layout)

§                     Tarpon Construction, Inc. (SBE) ($5,625) (asphalt paving)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments