Construct Barclay Downs Sidewalk
Action
Action:
Approve a contract in the amount of $924,190.56 to the lowest responsive bidder Dot Construction, Inc. for the Barclay Downs Sidewalk project.
Body
Staff Resource(s):
Phil Reiger, General Services
Jennifer Smith, General Services
Veronica Wallace, General Services
Explanation
§ Identified in the Southpark Comprehensive Neighborhood Improvement Program, this project will construct approximately 0.6 miles of new sidewalk along the east side of Barclay Downs Drive between Sayre Road/Scofield Road and Runnymede Lane in Council District 6.
§ Work includes sidewalk, curb and gutter, new curb ramps, and planting strip.
§ On September 22, 2020, the city issued an Invitation to Bid; nine bids were received.
§ Dot Construction, Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by third quarter 2021.
Charlotte Business INClusion
Dot Construction, Inc. is a city certified SBE.
Established MBE Goal: 7.00%
Committed MBE Goal: 7.00%
Dot Construction, Inc. met the established MBE subcontracting goal, and has committed 7.00% ($64,694) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ B & M Concrete, Inc. (MBE, SBE) ($58,624) (concrete)
§ Streeter Trucking Company, Inc. (MBE, SBE) ($6,070) (hauling)
Fiscal Note
Funding: General Capital Investment Plan
Attachments
Attachment(s)
Map