Title
Long Creek Pump Station Improvements
Action
Action:
Approve a guaranteed maximum price of $1,122,311 to The Haskell Company for the purchase of materials and equipment needed for Design-Build construction services for the Long Creek Pump Station Improvements project.
Body
Staff Resource(s):
David Czerr, Charlotte Water
Ron Hargrove, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ The Haskell Company has developed a guaranteed maximum price (GMP) for infrastructure improvements at the existing Long Creek Pump Station (adjacent to Council Districts 2 and 3). This work is associated with an overall project to accept wastewater from the City of Mount Holly into the future Stowe Regional Water Resource Recovery Facility.
§ On September 10, 2018, and on December 11, 2018, City Council previously adopted resolutions for this project with the City of Mount Holly.
§ City Council approved a contract with The Haskell Company for Design-Build design services on July 8, 2019, and for construction services on March 16, 2020.
§ Council will receive future requests for the approval of remaining project GMPs once they are established.
Disadvantaged Business Enterprise
This project is subject to the North Carolina Clean Water State Revolving Fund (CWSRF) loan program guidelines, which only require MWBE goals on Construction Contracts.
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map