Title: Collective Storm Drainage Improvement Projects Series F
Attachments: 1. Map_Collective Storm Drainage Improvement Projects Series F.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Collective Storm Drainage Improvement Projects Series F

 

Action

Action:

Approve a contract in the amount of $1,635,700 to the lowest responsive bidder Zoladz Construction Co., Inc. for Collective Storm Drainage Improvement Projects Series F.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Mike Davis, General Services

Susan Tolan, General Services

 

Explanation

§                     This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems.

§                     This contract will address failing storm drainage systems in the following locations:

-                     7100 Whitside Lane located in Council District 3,

-                     2725 Tanglewood Lane located in Council District 6,

-                     2122 Emerywood Drive located in Council District 6,

-                     3842 Rhodes Avenue located in Council District 6,

-                     6521 Seton House Lane located in Council District 7, and

-                     3901 Braxton Drive located in Council District 6.

§                     Work will also include grading, drainage, sidewalks, and curb and gutter.

§                     On May 4, 2020, the city issued an Invitation to Bid; five bids were received.

§                     Zoladz Construction Co., Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2021.

 

Charlotte Business INClusion

Established MBE Goal: 6.00%

Committed MBE Goal: 6.00%

Zoladz Construction Co., Inc. met the established MBE subcontracting goal and has committed 6.00% ($98,112) of the total contract amount to the following MBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     R.R.C. Concrete Inc. (MBE, SBE) ($44,000) (concrete)

§                     Diamond Trucking of NC Inc (MBE, SBE) ($54,112) (hauling)

 

Established SBE Goal: 16.00%

Committed SBE Goal: 16.00%

Zoladz Construction Co., Inc. met the established SBE subcontracting goal and has committed 16.00% ($261,632) of the total contract amount to the following SBE certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Maybury Fencing Inc (WBE, SBE) ($36,370) (fence)

§                     R.R.C. Concrete Inc. (MBE, SBE) ($44,000) (concrete)

§                     Diamond Trucking of NC Inc (MBE, SBE) ($54,112) (hauling)

§                     Whitesell Trucking, Inc. (SBE) ($60,200) (clearing)

§                     On Time Construction, Inc. (WBE, SBE) ($66,950) (masonry)


Fiscal Note

Funding:  Storm Water Capital Investment Plan

 