File #: 15-13513    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 6/1/2020 In control: City Council Business Meeting
On agenda: 7/13/2020 Final action:
Title: Upper McAlpine Creek Sanitary Sewer Interceptor Construction
Attachments: 1. Upper McAlpine Creek Sanitary Sewer Interceptor Design-Build Services - Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Upper McAlpine Creek Sanitary Sewer Interceptor Construction

 

Action

Action:

Approve a guaranteed maximum price of $17,078,883.69 to Crowder Constructors Inc. dba Crowder Construction Company for Design-Build construction services for the Upper McAlpine Creek Sanitary Sewer Interceptor project.

 

Body

Staff Resource(s):

David Czerr, Charlotte Water

Ron Hargrove, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This contract will provide 13,000 feet of 30-inch sanitary sewer pipe, extending from near Lawyer’s Road to near the Albemarle Road/Wilgrove-Mint Hill Road intersection (Council District 5).

§                     The project is needed to address existing sanitary sewer capacity limitations and accommodate future flows.

§                     Crowder Constructors Inc. dba Crowder Construction Company has developed a guaranteed maximum price (GMP) for construction of the Upper McAlpine Creek Sanitary Sewer Interceptor.

§                     On December 17, 2018, Council approved a contract with Crowder Constructors Inc. dba Crowder Construction Company for Design-Build design services. Based on the design, a GMP for construction services was developed.

§                     The project is expected to be complete by first quarter 2023. 

 

Charlotte Business INClusion

The city negotiates participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.4 of the Charlotte Business INClusion Policy). Crowder Constructors Inc. dba Crowder Construction Company has committed $3,010,520 or approximately 17.63% of the total contract for Design-Build construction services to the following certified firms:

§                     AMP Utility Distribution Services, LLC (WBE, SBE) ($881,360) (pipe material supply)

§                     Express Logistics Services, Inc. (MBE, SBE) ($551,000) (hauling stone)

§                     Fuller & Co. Construction, LLC (SBE) ($493,800) (construction tunneling)

§                     Capstone Civil Engineering, Inc. (MBE, SBE) ($364,000) (cctv inspections)

§                     R.E. Sifford Utility, Inc. (MBE, SBE) ($309,015) (sewer spot repairs)

§                     Sanders Constructors, Inc. (SBE) ($135,000) (clearing and grubbing)

§                     Lil Associates II, Inc. (MBE, SBE) ($78,000) (minority and small business consulting)

§                     Mid-Atlantic Erosion Control, Inc. (MBE, SBE) ($66,579) (erosion control, silt fence, tree protection)

§                     Martin Landscaping Company, Inc. (MBE, SBE) ($55,766) (erosion control, seeding)

§                     R. A. Piccalo, Inc. DBA PicTec, Inc. (SBE) ($39,000) (project scheduling services)

§                     Yellow Duck Marketing (WBE, SBE) ($37,000) (project communications)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan