Title: Charlotte Water Modular Units
Attachments: 1. Modular Building Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Charlotte Water Modular Units

 

Action

Action                     

Approve a contract in the amount of $1,218,768 to the lowest responsive bidder Swartz Building Solutions, Inc. for Charlotte Water modular units.

 

Body

Staff Resource(s):

David Czerr, Charlotte Water

Ron Hargrove, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This contract will allow for the purchase and installation of modular units to house maintenance staff at the Irwin Creek Wastewater Treatment Plant (Council District 3) and Zone 2 Field Operations Facility (Council District 1).

§                     On November 18, 2019, the city issued an Invitation to Bid (ITB); one bid was received.

-                     G.S. 143-132 prohibits municipalities from awarding construction contracts over $500,000 without receiving at least three competitive bids from the initial advertisement of the contract. The city may subsequently award the contract even if re-advertisements result in fewer than three competitive bids.

§                     On December 19, 2019, the ITB was re-issued; two bids were received.

§                     Swartz Building Solutions, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2020.

 

Charlotte Business INClusion

Established MSBE Goal: 10.00%
Committed MSBE Goal:  4.88%

Swartz Building Solutions, Inc. did not meet the established subcontracting goal at time of bid but earned the required Good Faith Effort points (Part B: Section 3 of the Charlotte Business INClusion Policy). Swartz Building Solutions, Inc. has committed 4.88% ($59,449) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     G & Y Masonry, Inc. (MBE, SBE) ($40,490) (masonry)

§                     Caryl Mechanical Inc. dba The Boswell Group (WBE, SBE) ($10,250) (plumbing)

§                     Buildout Services, LLC (SBE) ($5,750) (cabinet and countertop installation)

§                     Full Square Ventures dba 360 Degree Commercial Cleaning (SBE) ($2,959) (janitorial)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 