Title: Construct SouthPark Enhanced Crosswalks
Attachments: 1. Location Map - Construct Southpark Enhanced Crosswalk Ph 1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.
Title
Construct SouthPark Enhanced Crosswalks

Action
Action:
Approve a contract in the amount of $1,152,669.10 to the lowest responsive bidder Sealand Contractors Corp. for the SouthPark Enhanced Crosswalks.

Body
Staff Resource(s):
Phil Reiger, General Services
Mike Davis, General Services
Kristie Kennedy, General Services

Explanation
* This project, identified in the SouthPark Comprehensive Neighborhood Improvement Program (CNIP), will improve pedestrian safety and mobility at the intersections of Sharon Road/Fairview Road and Sharon Road/Morrison Boulevard in Council District 6.
* Work will include pavement resurfacing and the installation of high visibility crosswalks, curb ramps, and pedestrian countdown signals.
* On August 12, 2019, the city issued an Invitation to Bid; two bids were received.
* G.S. 143-132 prohibits municipalities from awarding construction contracts over $500,000 without receiving at least three competitive bids from the initial advertisement of the contract. The city may subsequently award the contract even if re-advertisements result in fewer than three competitive bids.
* On November 7, 2019, the city re-issued an Invitation to Bid; two bids were received.
* Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by second quarter 2020.

Charlotte Business INClusion
Established SBE Goal: 16.00%
Committed SBE Goal: 16.00%

Sealand Contractors Corp. met the established SBE subcontracting goal, and has committed 16.00% ($184,450) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Striping Concepts, LLC (SBE) ($115,250) (pavement markings)
* Diamond Trucking of NC Inc (SBE, MBE) ($69,200) (hauling)

Established MBE Goal: 6.00%
Committed MBE Goal: 6.00%

Sealand Contractors Corp. met the established MBE subcontracting goal, and has committed 6.00% ($69,200) of the total con...