City of Charlotte Banner
File #: 15-11538    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 8/8/2019 In control: City Council Business Meeting
On agenda: 11/25/2019 Final action:
Title: McAlpine Creek Wastewater Treatment Plant Grit System Upgrades
Attachments: 1. Map-McAlpine Creek Wastewater Treatment Plant Grit System Upgrades
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

McAlpine Creek Wastewater Treatment Plant Grit System Upgrades

 

Action

Action                     

Approve a contract in the amount of $4,960,000 to the lowest responsive bidder The Harper Corporation-General Contractors for the McAlpine Creek Wastewater Treatment Plant Grit System Upgrades project.

 

Body

Staff Resource(s):

David Czerr, Charlotte Water

Ron Hargrove, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This contract will provide an improved grit removal system for the McAlpine Creek Wastewater Treatment Plant (WWTP), located in the Town of Pineville (adjacent to Council District 7). 

§                     The grit removal system is a critical component of the wastewater treatment process and these upgrades will minimize maintenance and ensure the reliability of plant operations.

§                     On September 30, 2019, the city issued an Invitation to Bid; two bids were received.

-                     G.S. 143-132 prohibits municipalities from awarding construction contracts over $500,000 without receiving at least three competitive bids from the initial advertisement of the contract. The city may subsequently award the contract even if re-advertisements result in fewer than three competitive bids.

§                     On October 24, 2019, the city re-issued an Invitation to Bid; two bids were received.

§                     The Harper Corporation-General Contractors was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the first quarter of 2021.

 

Charlotte Business INClusion

Established MSBE Goal: 8.00%
Committed MSBE Goal: 9.24%

The Harper Corporation-General Contractors met the established subcontracting goal and has committed 9.24% ($458,428) of the total contract amount to the following certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     CITI, LLC (MBE) ($377,678) (instrumentation)

§                     HG Global Services, Inc. (SBE) ($80,750) (structural metals)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 

Attachments

Attachment(s)

Map