Title
Construct 25th Street Extension Project
Action
Action:
Approve a contract in the amount of $4,445,241.63 to the lowest responsive bidder Sealand Contractors Corp. for the 25th Street Extension Project.
Staff Resource(s):
Mike Davis, General Services
Tom Russell, General Services
Sharon Buchanan, General Services
Explanation
§ This project is part of the North East Corridor Infrastructure program and will include construction of a bridge over Little Sugar Creek extending 25th Street and improving connectivity to the LYNX Blue Line 25th Street Station in Council District 1.
§ Work will include curb, gutter, sidewalk, planting strips, street lighting, and street trees.
§ On August 20, 2019, the city issued an Invitation to Bid; four bids were received.
§ Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by first quarter 2021.
Charlotte Business INClusion
Established SBE Goal: 14.00%
Committed SBE Goal: 14.00%
Sealand Contractors Corp. met the established SBE subcontracting goal, and has committed 14.00% ($622,337.20) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ Cesar A. Leon L.L.C. (SBE, MBE) ($88,905) (hauling)
§ Diamond Trucking of NC Inc (SBE, MBE) ($88,905) (hauling)
§ Streeter Trucking Company, Inc. (SBE, MBE) ($88,905) (hauling)
§ R C Hauling, Inc. (SBE) ($85,025) (hauling)
§ On Time Construction, Inc. (SBE) ($84,998) (concrete, masonry)
§ AMP Utility Distribution Services, LLC (SBE) ($68,960) (utility material)
§ Maybury Fencing Inc. (SBE) ($46,900) (fence installation)
§ Clear Creek of Salisbury Inc (SBE) ($36,452.50) (concrete)
§ Habitat Assessment & Restoration Program, Inc. (SBE) ($19,131) (landscaping)
§ Striping Concepts, LLC (SBE) ($14,155.70) (pavement markings)
Established MBE Goal: 6.00%
Committed MBE Goal: 6.00%
Sealand Contractors Corp. met the established MBE subcontracting goal, and has committed 6.00% ($266,715) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ Cesar A. Leon L.L.C. (SBE, MBE) ($88,905) (hauling)
§ Diamond Trucking of NC Inc (SBE, MBE) ($88,905) (hauling)
§ Streeter Trucking Company, Inc. (SBE, MBE) ($88,905) (hauling)
Fiscal Note
Funding: General Capital Investment Plan
Attachments
Attachment(s)
Map