File #: 15-11122    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 5/30/2019 In control: City Council Business Meeting
On agenda: 7/22/2019 Final action: 7/22/2019
Title: Construct Charlotte Fire Station #43
Attachments: 1. Location Map - CFD Fire Station 43

Title

Construct Charlotte Fire Station #43

 

Action

Action                     

Approve a contract in the amount of $5,880,405.46 to the lowest responsive bidder Southside Constructors, Inc for the Charlotte Fire Department Fire Station #43 project.

 

Body

Staff Resource(s):

Mike Davis, General Services

William Haas, General Services

Reginald Johnson, Fire

Cynthia Bonham, Fire

 

Explanation

§                     Charlotte Fire Station #43 will include construction of a three-bay, 12,802-square foot facility at 421 Clanton Road, located in Council District 3.

§                     The new station is needed to meet the service needs of the surrounding area and improve emergency response times.

§                     This facility has been designed to achieve basic-level LEED version 4 certification per the city policy on sustainable facilities. LEED certification is awarded to buildings that demonstrate a high level of energy-efficiency and sustainable design.

§                     On June 2, 2019, the city issued an Invitation to Bid; four bids were received.

§                     Southside Constructors, Inc was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2020.

 

Charlotte Business INClusion

Established SBE Goal: 13.00%

Committed SBE Goal: 20.24%

Southside Constructors, Inc. exceeded the established SBE subcontracting goal, and has committed 20.24% ($1,066,241) of the base bid amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Bernard Irby Inc. (SBE, MBE) ($631,368) (electrical system)

§                     Ground Thunder Trucking, LLC (SBE) ($434,873) (concrete)

 

Established MBE Goal: 7.00%

Committed MBE Goal: 11.98%

Southside Constructors, Inc. exceeded the established MBE subcontracting goal, and has committed 11.98% ($631,368) of the base bid amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Bernard Irby Inc. (SBE, MBE) ($631,368) (electrical system)

 

Fiscal Note

Funding:  General Capital Investment Plan

 

Attachments

Attachment(s)

Map