Title: Construct Charlotte-Mecklenburg Police Department University City Division Station
Attachments: 1. Location Map - CMPD University City Division Station

Title

Construct Charlotte-Mecklenburg Police Department University City Division Station 

 

Action

Action:

Approve a contract in the amount of $9,503,205 to the lowest responsive bidder Miles-McClellan Construction Company, Inc. for the Charlotte-Mecklenburg Police Department University City Division Station project.

 

 

Body

Staff Resource(s):

Mike Davis, General Services

William Haas, General Services

Kerr Putney, Police

Estella Patterson, Police

 

Explanation

§                     The planned University City Division Police Station project includes construction of a 16,081-square-foot facility at 8452 North Tryon Street, located in Council District 4.

§                     The University City Division is currently occupying a leased property at 8401 University Executive Park Drive.

§                     In 2010, City Council approved the Facilities Strategic Plan for Police Stations. The goals for division stations in the Plan are:

-                     Owned and maintained by the city, not located in leased facilities,

-                     Constructed in highly visible and accessible locations that contribute to the community perception of safety and security,

-                     Sized to accommodate future personnel growth and support the functions a patrol division is expected to provide to the community,

-                     Designed to be highly recognizable as a CMPD division station while reflecting the exterior design context of the community where it is located, and

-                     Support the functional needs of a patrol division based on a standardized facility design template.

§                     This facility has been designed to achieve basic-level LEED version 4 certification per the City Policy on Sustainable Facilities.

§                     On May 10, 2019, the city issued an Invitation to Bid; no bids were received.

§                     On June 26, 2019, the city re-issued an Invitation to Bid; four bids were received.

§                     Miles-McClellan Construction Company, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2020.

 

Charlotte Business INClusion

Established SBE Goal: 15.00% 

Committed SBE Goal: 15.01%

 

Miles-McClellan Construction Company, Inc. met the established SBE subcontracting goal, and has committed 15.01% ($1,358,617) of the base bid amount (excluding allowances of $329K) to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Bernard Irby Inc. (SBE, MBE) ($932,545) (electrical, fire alarm)

§                     Carroll Small Repairs (SBE, MBE) ($260,500) (acoustical ceilings, carpentry, door install, sitework)

§                     Maybury Fencing Inc. (SBE) ($165,572) (fencing)

 

Established MBE Goal: 5.00%

Committed MBE Goal: 20.11%

 

Miles-McClellan Construction Company, Inc. exceeded the established MBE subcontracting goal, and has committed 20.11% ($1,820,545) of the base bid amount (excluding allowances of $329K) to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Bernard Irby Inc. (SBE, MBE) ($932,545) (electrical, fire alarm)

§                     A-1 Glass & Aluminum, LLC (MBE) ($627,500) (aluminum storefront, interior glass)

§                     Carroll Small Repairs (SBE, MBE) ($260,500) (acoustical ceilings, carpentry, door install, sitework)


Fiscal Note

Funding:  General Capital Investment Plan

 