City of Charlotte Banner
File #: 15-9331    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 10/3/2018 In control: City Council Business Meeting
On agenda: 1/14/2019 Final action: 1/14/2019
Title: Franklin and Dukes Water Treatment Plants Improvements
Attachments: 1. Map 1-Water Treatment Plant Water Quality Optimization and Fluoride System and Fire Alarm Improvements, 2. Map 2-Water Treatment Plant Water Quality Optimization and Fluoride System and Fire Alarm Improvements
Title
Franklin and Dukes Water Treatment Plants Improvements

Action
Action:
A. Approve a contract in the amount of $5,615,000 to the lowest responsive bidder The Harper Corporation-General Contractors for the Franklin and Dukes Water Treatment Plant improvement projects, and

B. Approve a contract for up to $675,660 with Hazen and Sawyer for engineering services.

Body
Staff Resource(s):
Angela Lee, Charlotte Water
Ron Hargrove, Charlotte Water
Carl Wilson, Charlotte Water

Explanation
Action A
* This contract will replace chemical feed systems at the Franklin Water Treatment Plant (WTP), located on Brookshire Boulevard (Council District 2), and the fluoride storage system and fire alarm system at the Lee S. Dukes WTP, located in the Town of Huntersville (adjacent to Council Districts 2 and 4).
* On November 9, 2018, the City issued an Invitation to Bid; three bids were received.
* The Harper Corporation-General Contractors was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by the second quarter of 2020.

Action B
* This contract provides engineering services for construction administration, construction surveying, and inspection services for both projects.
* On March 23, 2015, City Council approved a contract with Hazen and Sawyer for the design of water quality optimization recommendations, including the design of the Franklin WTP improvements project. The approval also included the selection of Hazen and Sawyer for future phases of work on the project, including the current contract request for construction related engineering services for the project.
* On July 24, 2017, Council approved a contract with Hazen and Sawyer for miscellaneous engineering services, which included the design of the Dukes WTP improvements project.
* For efficiency of engineering resources, and to increase competition during the bid phase, it was decided to combine the design projects into one construction contract, adminis...

Click here for full text