Title
Airport Terminal Lobby Expansion Amendment
Action
Action:
Approve contract amendment #1 in the amount of $770,806 with GS&P/NC, P.C. for additional architectural and engineering design services for the Terminal Lobby Expansion project.
Body
Staff Resource(s):
Brent Cagle, Aviation
Jack Christine, Aviation
Explanation
§ During the design process for Terminal Lobby Expansion, the need for a Central Energy Plant (CEP) was identified in order to serve the utilities for the building expansion.
§ As design progressed, it was determined that modifications were required for Checkpoint E for increased passenger throughput during construction. The modifications will include new screening equipment and modifications to the existing infrastructure.
§ This amendment provides necessary design service to accommodate changes to the CEP and Checkpoint E.
§ On October 23, 2017, City Council approved a contract in the amount of $21,750,000 with GS&P/NC, P.C. for architectural and engineering design services, as well as project coordination activities for the Terminal Lobby Expansion project.
§ The new total amount of the contract, including amendment #1, will be $22,520,806.
§ This activity is occurring on airport property (Council District 3).
Charlotte Business INClusion
All additional work involved in this amendment will be performed by GS&P/NC, P.C. and their existing subconsultants (Part D: Section 6 of the Charlotte Business INClusion Policy).
GS&P/NC, P.C. has committed 13.46% ($103,739) of the total contract amendment amount to the following certified firms:
§ Laurene, Ricker & Sorrell, PC (SBE) ($71,239) (structural design)
§ DAS Architecture, Inc. (SBE) ($32,500) (architectural services)
Fiscal Note
Funding: Aviation Community Investment Plan