Title: Airport Sanitary Sewer Line

Title

Airport Sanitary Sewer Line

 

Action

Action                     

Approve a contract in the amount of $5,564,286.19 to the lowest responsive bidder Fuller & Co. Construction LLC for the Sanitary Sewer Line on Rental Car Road.

 

Body

Staff Resource(s):

Brent Cagle, Aviation

Jack Christine, Aviation

 

Explanation

§                     Due to increased sewer demand from Concourse A Expansion and the Terminal Lobby Expansion projects, a new sewer line is necessary for these and future projects.

§                     On July 24, 2017, City Council approved sewer design services for the Concourse A and Terminal Lobby Expansion projects in the amount of $399,400 by STV Engineers, Inc.

§                     On July 17, 2018, the City issued an Invitation to Bid; three bids were received.

§                     Fuller & Co. Construction LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2019.

§                     This activity is occurring on airport property, Council District 3.

 

Charlotte Business INClusion

Fuller & Co Construction LLC is a City certified SBE. Current Charlotte Business INClusion Policy does not count the prime contractor’s certification status towards MSBE subcontracting goals.

 

Established MSBE Goal: 9.00%

Committed MSBE Goal (at time of Bid): 1.75%

MSBE Participation to Date: 5.47% 

Fuller & Co Construction LLC failed to meet the established subcontracting goal, but earned the minimum Good Faith Effort Points (Part B: Section 5 of the Charlotte Business INClusion Policy). Fuller & Co Construction LLC committed:

§                     Tarpon Construction, Inc. (SBE) ($96,000) (asphalt, curb, and sidewalk)

 

Subsequent to the Bid Opening, Fuller & Co Construction LLC has committed an additional 3.72% ($208,300) to the following certified firms :

§                     Tony’s Trucking (SBE, MBE) ($75,000) (hauling)

§                     Carolina Environmental Response Team (SBE) ($60,075) (vacuum excavation)

§                     Kelby Construction, Inc (SBE) ($36,125) (traffic control, landscape lighting, landscaping)

§                     Supreme Sweepers (MBE) ($17,500) (sweeping site pavement)

§                     The Survey Company (SBE) ($15,000) (survey)

§                     RDL Private Utility (SBE, MBE) ($4,600) (utility locating)

 

City staff will continue to work with Fuller & Co Construction to increase MSBE participation.

 