File #: 15-8777    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 7/13/2018 In control: City Council Business Meeting
On agenda: 9/10/2018 Final action: 9/10/2018
Title: Oakdale Road Widening
Attachments: 1. Location Map - Oakdale Road Widening

Title

Oakdale Road Widening

 

Action

Action                     

Approve a contract in the amount of $8,648,187.89 to the lowest responsive bidder Sealand Contractors Corp. for the Oakdale Road Widening project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

Veronica Wallace, Engineering and Property Management

Leslie Bing, Engineering and Property Management

 

Explanation

§                     This project will improve safety, reduce congestion, and provide accommodations for pedestrians, bicyclists and transit users along Oakdale Road from Old Plank Drive to Dale Avenue (approximately 1 mile), located in Council District 2.

§                     Work will include widening the existing road to a two-lane road with a median/turn lane, bicycle lanes, sidewalk, curb and gutter, storm drainage, planting strips, retaining walls, and street lighting.

§                     Construction will also include:

-                     Two culvert replacements along Dale Avenue,

-                     Storm drainage pipe and structures,

-                     Sanitary sewer pipe and structures, and

-                     Channel improvements.

§                     On July 17, 2018, the City issued an Invitation to Bid; three bids were received.

§                     Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2020.

 

Charlotte Business INClusion

Established SBE Goal: 22.00%

Committed SBE Goal: 22.00%

 

Sealand Contractors Corp. met the established SBE subcontracting goal, and has committed 22.00% ($1,902,608.30) of the total contract amount to the following certified SBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Darnell Jones Trucking, Inc. (SBE, MBE) ($475,000) (hauling)

§                     On Time Construction, Inc. (SBE) ($310,550) (concrete)

§                     Cochise Trucking (SBE) ($289,500) (hauling)

§                     Affordable Source Trucking, LLC (SBE, MBE) ($281,400) (hauling)

§                     Buffkin Trucking, Inc. (SBE, MBE) ($281,400) (hauling)

§                     Maybury Fencing Inc. (SBE) ($85,455) (fence)

§                     AMP Utility Distribution Services, LLC (SBE) ($63,000) (utility material)

§                     Ground Effects, Inc. (SBE, WBE) ($60,879.30) (pavement markings)

§                     R & N Construction Group, LLC (SBE, WBE) ($42,920) (retaining wall)

§                     Erosion Defence, LLC (SBE) ($12,504) (erosion control)

 

Established MBE Goal: 9.00%

Committed MBE Goal: 12.00%

 

Sealand Contractors Corp. exceeded the established MBE subcontracting goal, and has committed 12.00% ($1,037,800) of the total contract amount to the following certified MBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Darnell Jones Trucking, Inc.(SBE, MBE) ($475,000) (hauling)

§                     Affordable Source Trucking, LLC  (SBE, MBE) ($281,400) (hauling)

§                     Buffkin Trucking, Inc.  (SBE, MBE) ($281,400) (hauling)

 

Fiscal Note

Funding:  General Community Investment Plan

 

Attachments

Attachment(s)

Map