Title
Airport Concourse A Renovation - Construction Manager At Risk and Construction Materials Testing Services
Action
Action:
A. Approve a contract in the amount of $42,585,401.91 with Turner-Rodgers, A Joint Venture, for Construction Manager At Risk services for the Concourse A Renovation project, and
B. Approve a contract in the amount of $224,510 with Froehling & Robertson, Inc. for construction materials testing and special inspections.
Body
Staff Resource(s):
Brent Cagle, Aviation
Jack Christine, Aviation
Explanation
* The Aviation Department is renovating large portions of Concourse A to enhance customer experience. The existing Concourse A will be renovated to include new ceilings, wall finishes, flooring, mechanical system upgrades, and LED lighting, as well as expanded to increase passenger holdroom, restroom, and tenant concession capacity.
* The project is anticipated to be complete by the fourth quarter of 2019.
* This activity is occurring on airport property, which is in Council District 3.
Action A
* As the Construction Manager At Risk, Turner-Rodgers is responsible for:
* Scheduling and managing all phases of construction and the performance of all of its contractors in the construction of the project,
* Prequalifying first tier prime contractors as required by state statute and City of Charlotte prequalification guidelines,
* Organizing the work into bid packages, conducting a public bidding process for each subcontracting opportunity, and awarding each package to the lowest responsive, responsible bidder, and
* Managing construction to completion under State of North Carolina Construction Manager At Risk statute.
* On September 8, 2017, the Aviation Department issued Request for Qualifications for general contracting firms to submit qualifications for Construction Manager At Risk for the Concourse A Renovation project; the City received three proposals from interested firms.
* Turner-Rodgers, A Joint Venture was selected based on its r...