City of Charlotte Banner
File #: 15-7272    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 1/3/2018 In control: City Council Business Meeting
On agenda: 2/26/2018 Final action: 2/26/2018
Title: Ayrsley Town Boulevard Improvement Project
Attachments: 1. Location Map - Ayrsley Town Boulevard

Title

Ayrsley Town Boulevard Improvement Project

 

Action

Action                     

Award a contract in the amount of $691,647 to the lowest responsive bidder Blythe Development Co. for the Ayrsley Town Boulevard Project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

Becky Chambers, Engineering and Property Management

 

Explanation

§                     This project will include the construction of sidewalk, curb, gutter and storm drainage along Ayrsley Town Boulevard from South Tryon Street to Kings Parade Boulevard, located in Council District 3.  The goal of this project is to improve pedestrian safety and mobility and was identified in the Whitehall/Ayrsley Comprehensive Neighborhood Improvement Program.  

§                     On January 12, 2018, the City issued an Invitation to Bid; five (05) bids were received from interested service providers.

§                     Blythe Development Co. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by first quarter 2019.


Charlotte Business INClusion

Established SBE Goal: 18.00%

Committed SBE Goal: 26.03%

Blythe Development exceeded the established subcontracting goal, and has committed 26.03% ($180,025) of the total contract amount to the following certified firms:

§                     Abram Construction (SBE, MBE) ($168,025) (sidewalk, storm drain)

§                     Express Logistics (SBE, MBE) ($12,000) (hauling)

 

Established MBE Goal: 8.00 %

Committed MBE Goal: 26.03%

Blythe Development exceeded the established subcontracting goal, and has committed 26.03% ($180,025) of the total contract amount to the following certified firms:

§                     Abram Construction (MBE, SBE) ($168,025) (sidewalk, storm drain)

§                     Express Logistics (MBE, SBE) ($12,000) (hauling)

 

Fiscal Note

Funding: General Community Investment Plan

 

Attachments

Attachment(s)

Map