City of Charlotte Banner
File #: 15-6784    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 10/17/2017 In control: City Council Business Meeting
On agenda: 12/11/2017 Final action: 12/11/2017
Title: West Morehead and I-77 Pedestrian Improvements Project
Attachments: 1. Location Map - West Morehead and I-77 Pedestrian Improvements Project

Title

West Morehead and I-77 Pedestrian Improvements Project

 

Action

Action                     

Award a contract in the amount of $319,541.75 to the lowest responsive bidder B & N Grading, Inc. for the West Morehead and I-77 Pedestrian Improvements project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management
Chandler Crofts, Engineering and Property Management

 

Explanation

§                     This project was selected because there is a significant need to upgrade the existing pedestrian facilities in order to provide a safer connectivity to Center City and the surrounding neighborhoods.

§                     The scope for this project will include new curb and gutter, wider sidewalks, wheelchair ramps, pedestrian lighting, and street resurfacing.

§                     The goal of this project is to enhance pedestrian safety at West Morehead Street and I-77 (approximately 0.2 mile).  The City has identified this location as a priority due to high traffic volumes. 

§                     On October 13, 2017, the City issued an Invitation to Bid; four bids were received from interested service providers.

§                     B & N Grading, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by second quarter of 2018.

 

Charlotte Business INClusion

Established SBE Goal: 10.00%

Committed SBE Goal: 10.31%

B & N Grading, Inc. exceeded the established SBE subcontracting goal, and has committed 10.31% ($32,931.26) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Silverback Brothers LLC (SBE, MBE) ($17,931.26) (grading)

§                     RPG Construction LLC (SBE, MBE) ($15,000) (pavement)

 

Established MBE Goal: 5.00%

Committed MBE Goal: 10.31%

B & N Grading, Inc. exceeded the established MBE subcontracting goal, and has committed 10.31% ($32,931.26) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Silverback Brothers LLC (SBE, MBE) ($17,931.26) (grading)

§                     RPG Construction LLC (SBE, MBE) ($15,000) (pavement)

 

Fiscal Note

Funding: General Community Investment Plan

 

Attachments

Attachment(s)

Map