File #: 15-6169    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 7/18/2017 In control: City Council Business Meeting
On agenda: 9/11/2017 Final action: 9/11/2017
Title: Seneca Place and Wedgewood Drive Intersection and Storm Drainage Improvements
Attachments: 1. Location Map - Seneca Place and Wedgewood Drive Intersection

Title

Seneca Place and Wedgewood Drive Intersection and Storm Drainage Improvements

 

Action

Action                     

Award a contract in the amount of $915,200 to the lowest responsive bidder Zoladz Construction Co., Inc. for the Seneca Place and Wedgewood Drive Intersection and Storm Drainage Improvements project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

Becky Chambers, Engineering and Property Management

Stewart Edwards, Engineering and Property Management

 

Explanation

§                     This project will rebuild the intersection of Wedgewood Drive and Seneca Place with new curb and gutter, sidewalk and curb ramps to improve pedestrian safety.  This project will also install a new storm drainage system including box culverts, headwalls, pipes and catch basins along Seneca Place between Wedgewood Drive and Lamont Drive. 

§                     This project is an opportunity to minimize construction impacts by addressing requests for pedestrian safety and storm drainage improvements simultaneously in the neighborhood.

§                     On June 27, 2017, the City issued an Invitation to Bid; four bids were received from interested service providers.

§                     Zoladz Construction Co., Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2018.


Charlotte Business INClusion

Established SBE Goal: 15.00%

Committed SBE Goal: 15.92%

Zoladz Construction Co., Inc. exceeded the established SBE subcontracting goal, and has committed 15.92% ($145,740) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     On Time Construction, Inc. (SBE, MBE) ($91,000) (masonry)

§                     McCloud Construction, LLC (SBE) ($36,740) (concrete)

§                     Trull Contracting, LLC  (SBE, WBE) ($18,000) (asphalt/paving)

 

Established MBE Goal: 5.00%

Committed MBE Goal: 9.94%

Zoladz Construction Co., Inc. exceeded the established MBE subcontracting goal, and has committed 9.94% ($91,000) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     On Time Construction, Inc. (SBE, MBE) ($91,000) (masonry)

 

Fiscal Note

Funding: General and Storm Water Community Investment Plans

 