City of Charlotte Banner
File #: 15-5614    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 5/16/2017 In control: City Council Business Meeting
On agenda: 6/12/2017 Final action: 6/12/2017
Title: 1633 Starbrook Drive Storm Drainage Improvement Project
Attachments: 1. Location Map - 1633 Starbrook Drive Storm Drainage Improvement Project

Title

1633 Starbrook Drive Storm Drainage Improvement Project

 

Action

Action:

Award a contract in the amount of $736,238.40 to the lowest responsive bidder Harvest Environmental Services, Inc. for the 1633 Starbrook Drive Storm Drainage Improvement Project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

Stewart Edwards, Engineering and Property Management

 

Explanation

§                     The project will install approximately 770 feet of new storm drainage and replace associated utilities along Starbrook Drive, Wrentree Drive and Woodstream Drive.

§                     The work will include, but is not limited to:

-                     Storm drainage,

-                     Sidewalk,

-                     Curb and gutter,

-                     Driveways, and

-                     Asphalt pavement replacement.

§                     On April 12, 2017, the City issued an Invitation to Bid for the 1633 Starbrook Drive Storm Drainage Improvement Project. Only two bids were received. Since a minimum of three bidders are required to open per North Carolina General Statute, the project was re-advertised on May 2, 2017; two bids were received from interested service providers. 

§                     Harvest Environmental Services, Inc. was selected as the lowest responsive, responsible bidder.

§                     City Council approval includes authorization to use budgeted project funds allocated as contingency for subsequent change orders and/or amendments, which may be required for project completion.

§                     The project is anticipated to be complete by the end of fourth quarter 2017.

 

Charlotte Business INClusion

Established SBE Goal: 12.00%

Committed SBE Goal: 14.98%

Harvest Environmental Services, Inc. exceeded the established SBE subcontracting goal, and has committed 14.98% ($110,325) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     Trull Contracting, LLC (SBE, WBE) ($50,365) (asphalt)

                     Abram Construction Inc. (SBE, MBE) ($41,881) (concrete and storm drainage)

                     Maybury Fencing Inc. (SBE, WBE) ($11,079) (fencing)

                     Jones Grading & Fencing, Inc. (SBE, MBE) ($4,000) (hauling)

                     All Points Trucking, Inc. (SBE, WBE) ($3,000) (hauling)

 

Established MBE Goal: 6.00%

Committed MBE Goal: 6.23%

Harvest Environmental Services, Inc. exceeded the established MBE subcontracting goal, and has committed 6.23% ($45,881) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     Abram Construction Inc. (SBE, MBE) ($41,881) (concrete and storm drainage)

                     Jones Grading & Fencing, Inc. (SBE, MBE) ($4,000) (hauling)

 

Fiscal Note

Funding:  Storm Water Services Community Investment Plan

 

Attachments

Attachment(s)

Map