Title
Traffic Signal Work Associated with the Independence Boulevard Widening Project
Action
Action:
Adopt a resolution authorizing the City Manager to execute a Supplemental Agreement with the North Carolina Department of Transportation for performing traffic signal work associated with the Independence Boulevard Widening project.
Body
Staff Resource(s):
Danny Pleasant, Transportation
Charles Abel, Transportation
Explanation
§ The North Carolina Department of Transportation (NCDOT) has authorized the City to perform all traffic signal work for the installation of a new traffic signal at the intersection of Independence Boulevard and Sharon Forest Drive associated with the Independence Boulevard widening project.
§ The signal is being installed to eliminate a recurring crash pattern for left turning vehicles from Independence Boulevard onto Sharon Forest Drive, and to serve the increased U-turns at this intersection after multiple median closures along Independence Boulevard.
§ This signal will serve left turning vehicles in both directions as well as pedestrians crossing Independence Boulevard.
§ The need for a signal at this intersection was identified after the original municipal agreement was approved.
§ A Supplemental Agreement with NCDOT is needed in order for the City to be fully reimbursed for the work it performs.
§ On April 8, 2013, a Municipal Agreement for traffic signal work associated with the widening of Independence Boulevard in an amount up to $472,000 was approved by City Council.
§ This Supplemental Agreement is for reimbursement of up to $148,800 for a maximum reimbursement of $620,800.
§ The format and cost sharing philosophy is consistent with past Municipal Agreements
Fiscal Note
Funding: Reimbursement by North Carolina Department of Transportation