File #: 15-9497    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 10/26/2018 In control: City Council Business Meeting
On agenda: 3/25/2019 Final action: 3/25/2019
Title: Hough Road Storm Drainage Improvement Project
Attachments: 1. Location Map - Hough Road Storm Drainage Improvement Project

Title

Hough Road Storm Drainage Improvement Project

 

Action

Action                     

Approve a contract in the amount of $731,935.33 to the lowest responsive bidder United of Carolinas, Inc. for the Hough Road Storm Drainage Improvement Project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

Harold Gaines, Engineering and Property Management

 

Explanation

§                     The 4118 Hough Road Storm Drainage Improvement Project will address failing drainage systems on Hough Road, Heather Lane and Bevis Drive in Council District 1.

§                     Construction will include the installation storm drainage, drainage system rehabilitation, incidental paving and curb and gutter.

§                     On January 25, 2019, the City issued an Invitation to Bid; four bids were received.

§                     United of Carolinas, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by first quarter of 2020.

 

Charlotte Business INClusion

Established SBE Goal: 19.00%

Committed SBE Goal: 19.00%

 

United of Carolina, Inc. met the established SBE subcontracting goal, and has committed 19.00% ($139,100) of the total contract amount to the following certified SBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     J&R Tough Construction, Corp (SBE, MBE) ($98,000) (various construction)

§                     B&N Grading, Inc (SBE) ($28,000) (asphalt paving)

§                     Cesar A Leon LLC (SBE, MBE) ($13,100) (hauling)

 

Established MBE Goal: 7.00%

Committed MBE Goal: 15.18%

 

United of Carolina, Inc. exceeded the established MBE subcontracting goal, and has committed 15.18% ($111,100) of the total contract amount to the following certified MBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     J&R Tough Construction, Corp (SBE, MBE) ($98,000) (various construction)

§                     Cesar A Leon LLC (SBE, MBE) ($13,100) (hauling)

 

Fiscal Note

Funding:  Storm Water Community Investment Plan

 