Title
Airport Fire Protection Improvements Change Order
Action
Action:
Approve change order #1 for $3,358,888 to Messer Construction Co. for Construction Manager at-Risk services for the Federal Inspections Station Facility and Concourse D Renovations project.
Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation
Explanation
§ On August 22, 2022, City Council approved a contract with Messer Construction Co. in the amount of $4,448,091 for Construction Management at-Risk services for the Federal Inspection Station Facility and Concourse D Renovations project.
§ This change order will provide for the purchase and installation of new fire protection system equipment on the lower-level of Concourse D required to bring the terminal into compliance with NC State Building Code.
§ The new total value of the contract is $7,806,979.
Charlotte Business INClusion
Established MBE Goal: 10.27%
Committed MBE Goal: 10.27%
Messer Construction Co. met the established contract goal for this Change Order, committing to 10.27% ($344,802) of the total contract Change Order amount to the following certified firm(s):
§ All Pro Builders (MBE) ($298,034) (general construction)
§ Besco Electric (MBE) ($46,768) (electrical)
Fiscal Note
Funding: Aviation Capital Investment Plan