Title
Municipal Agreement for Relocation of Water and Sewer Infrastructure
Action
Action:
A. Adopt a resolution authorizing the City Manager to execute a Municipal Agreement with the North Carolina Department of Transportation for construction of water and sewer line relocations, adjustments, and improvements, and
B. Authorize the City Manager to approve the reimbursement request for the actual cost of the utility construction.
Body
Staff Resource(s):
Angela Lee, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ This Municipal Agreement is for the relocation and replacement of 1,400 linear feet of water and sewer lines located within the North Carolina Department of Transportation’s (NCDOT) highway improvements project (Project U-5804B), located on South Trade Street from Four Mile Creek to Weddington Road in the Town of Matthews (adjacent to Council District 7).
§ As required by the NCDOT’s encroachment agreements, the City is financially responsible for the cost to relocate City-owned water and sewer lines within the State maintained right-of-way.
§ The City will reimburse the NCDOT for actual construction costs at the conclusion of the project.
§ The format and cost-sharing philosophy of this Agreement is consistent with prior Municipal Agreements.
§ The total estimated cost of this construction within the project is $608,084.
Fiscal Note
Funding: Charlotte Water Community Investment Plan