File #: 15-21202    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 9/11/2023 In control: City Council Business Meeting
On agenda: 11/13/2023 Final action: 11/13/2023
Title: Construct Pebblestone Drive Storm Drainage Improvement Project
Attachments: 1. 15-21202 Construct Pebblestone Drive Storm Drainage Improvement Project

Title

Construct Pebblestone Drive Storm Drainage Improvement Project

 

Action

Action                     

A.                     Reject the low-bid submitted by Onsite Development, LLC. for the Pebblestone Drive Storm Drainage Improvement Project,

 

B.                     Approve a contract in the amount of $1,692,421.65 to the lowest responsive bidder Zoladz Construction Co., Inc. for the Pebblestone Drive Storm Drainage Improvement Project, and

 

C.                     Authorize the City Manager to amend the contracts consistent with the purpose for which the contracts were approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Matt Gustis, Storm Water Services

 

Explanation

§                     The project will improve aging infrastructure in the McAlpine Creek watershed along Creekridge Road, in District 6.

§                     Construction will include the installation of stream enhancement, retaining walls, water/sanitary sewer, curb, and gutter.

§                     On August 24, 2023, the city issued an Invitation to Bid; three bids were received.

§                     Zoladz Construction Co., Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter of 2024.

§                     The low bid submitted by Onsite Development, LLC. was found not to be responsible for this bid.

 

Charlotte Business INClusion  

Established MBE Goal: 5.00%

Committed MBE Goal: 5.00%

Zoladz Construction Co., Inc. met the established subcontracting goal and has committed approximately 5.00% ($84,600) of the contract amount to the following certified firms:

§                     Diamond Trucking of NC, Inc. (MBE, SBE) ($84,600) (hauling)

 

Established WBE Goal: 4.00%

Committed WBE Goal: 4.00%

Zoladz Construction Co., Inc. met the established subcontracting goal and has committed approximately 4.00% ($67,690) of the contract amount to the following certified firms:

§                     Trull Contracting, LLC (SBE, WBE) ($57,200) (concrete, asphalt)

§                     Pentacle, Inc. (SBE, WBE) ($10,490) (fencing)

 

Fiscal Note

Funding:  Storm Water Capital Investment Plan