Title
Construct Storm Drainage Improvement Projects
Action
Action:
A. Approve a contract in the amount of $2,746,696.70 to the lowest responsive bidder Zoladz Construction Co., Inc. for the Collective Storm Drainage Improvement Project - Series AB, and
B. Authorize the City Manager to amend the contracts consistent with the purpose for which the contracts were approved.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Logan Oliver, Storm Water Services
Explanation
§ The contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems.
§ The contract will address storm drainage systems at:
- 4323 La Brea Drive (Council District 2)
- 4625 Colony Road (Council District 6)
- 7944 Rolling Creek Court (Council District 6)
- 923 Kings Drive (Council Districts 1 and 6)
§ On September 18, 2023, the city issued an Invitation to Bid; four bids were received.
§ Zoladz Construction Co., Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by first quarter of 2025.
Charlotte Business INClusion
Established MBE Goal: 7.00%
Committed MBE Goal: 7.00%
Zoladz Construction Co., Inc. met the established subcontracting goal and has committed approximately 7.00% ($192,300) of the contract amount to the following certified firm:
§ Diamond Trucking of NC, Inc. (MBE, SBE) ($192,300) (hauling)
Established WBE Goal: 4.00%
Committed WBE Goal: 4.00%
Zoladz Construction Co., Inc. met the established subcontracting goal and has committed approximately 4.00% ($109,900) of the contract amount to the following certified firms:
§ Trull Contracting, LLC (SBE, WBE) ($70,900) (concrete, asphalt)
§ On Time Construction, Inc. (SBE, WBE) ($25,000) (masonry, CIP concrete)
§ Pentacle, Inc. (SBE, WBE) ($14,000) (fencing)
Fiscal Note
Funding: Storm Water Capital Investment Plan