File #: 15-10578    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 3/15/2019 In control: City Council Business Meeting
On agenda: 5/13/2019 Final action: 5/13/2019
Title: McAlpine Creek Wastewater Treatment Plant Reliability and Process Improvements Design-Build Construction Phase
Attachments: 1. Map-McAlpine Creek Wastewater Treatment Plant Reliability and Process Improvements Design-Build Construction Phase
Title
McAlpine Creek Wastewater Treatment Plant Reliability and Process Improvements Design-Build Construction Phase

Action
Action:
Approve a guaranteed maximum price of $57,560,798 to Garney Companies, Inc. for the purchase of wastewater treatment equipment needed for Phase 3 Design-Build Services for the McAlpine Creek Wastewater Treatment Plant Reliability and Process Improvements project.

Body
Staff Resource(s):
Angela Lee, Charlotte Water
Ron Hargrove, Charlotte Water
Carl Wilson, Charlotte Water

Explanation
* This action will approve the guaranteed maximum price (GMP) for the purchase and installation of equipment required to complete a major component of the McAlpine Creek Wastewater Treatment Plant (WWTP) Reliability and Process Improvements project, in the Town of Pineville (adjacent to Council District 7).
* Equipment will be purchased all at once to receive significant volume discounts and reduce the risk of future price escalation.
* This project will rehabilitate or replace critical components of the wastewater treatment process systems at the McAlpine Creek WWTP to ensure reliable discharge permit compliance.
* On February 26, 2018, Council approved a contract with Garney Companies, Inc. for Phase 1 Design-Build Services for design of a full-scale process pilot with associated tasks.
* On May 14, 2018, Council approved a contract with Garney Companies, Inc. for Phase 2a construction of the full-scale process pilot, analysis of data resulting from the pilot, and recommendations of options for future phases of the project.
* On January 14, 2019, Council approved a contract with Garney Companies, Inc. for the Phase 2b purchase of wastewater treatment equipment and professional services for design.
* This project will be designed and constructed in phases over a span of up to five years and has an estimated construction cost of approximately $120,000,000.
* Council will receive requests for the approval of remaining project GMPs.

Charlott...

Click here for full text